Solar expansion plan for Decatur draws opposition

August 21, 2025

Residents register opposition to proposed solar project by islands’ energy co-op.

[Updated Aug. 21, 2025]

Orcas Power and Light Co-Op — OPALCO — hoped a second solar project on Decatur Island would kill two birds with one stone by allowing the electric utility co-op to keep a state grant and better prepare for a projected increase in energy demands. 

But the proposed project’s main product so far seems to be a break in trust from residents on Decatur Island, where the company is proposing installing a few thousand more panels. 

“OPALCO went about this about as poorly as you possibly could,” said Kendra Lamb, whose family has lived on Decatur since the mid-1800s. 

In March, OPALCO purchased a 20-acre parcel on the island. The purchase came as a surprise to residents. 

OPALCO spokesperson Krista Bouchey said that while the company held its first community meeting with residents before the purchase, it did not have a complete list of residents at that point in time. 

“We have since rectified our contact list and have held an in-person meeting on Decatur Island (in May) that was also offered virtually, we have been sending regular email updates, and we have a project page on our website that has regularly updated materials,” Bouchey wrote in an email.

Dawni Cunnington, who has lived in Decatur for 25 years, argued that “it’s just not that difficult to figure out how to contact people.”

Decatur Island lies along Rosario Strait in the San Juan archipelago. (PNW Nat’l. Lab.)

“They’re able to contact me when my bill’s late or they’re going to have an outage … so it just does not seem like they earnestly are listening,” she said. 

Lamb, meanwhile, thinks it may be too late for the co-op to rebuild bridges. She said trust between Decatur residents and OPALCO has deteriorated so much that she doesn’t see any version of the project winning support from residents. 

“The vast majority — I’m talking about 95% of the island — does not want this. But they just don’t want to listen,” she said. 

The rift between many Decatur residents and OPALCO is a stark shift from the first time the utility co-op launched a solar project on the island in 2018. That microgrid project covers 3.6 acres. 

Decatur residents supported that project, said Lamb and Cunnington. At the council meeting, residents claimed OPALCO did not follow through on promises to landscape and maintain the project, which Lamb and Cunnington said has caused runoff issues for neighboring properties. 

“Much of our community is pro solar, but I think that people want to see a better solution than the destruction of beautiful acreage here in the San Juans,” Lamb said.   

One door closes, another opens?

The Decatur project isn’t OPALCO’s only proposed solar project. In fact, OPALCO only began exploring a second Decatur solar project after it ran into permitting issues for its Bailer Hill project on San Juan Island. 

The county’s Department of Community Development postponed the permitting process for the Bailer Hill project until OPALCO provides additional information about the project site and potential impacts. OPALCO still owns the land and plans on pursuing the project, likely sometime next year, according to Bouchey. 

The pause, however, meant OPALCO was in danger of losing a $1 million grant from the state Department of Commerce. 

“We were not going to be able to meet the grant timeline which is why we began exploring the site on Decatur Island,” Bouchey said. “We are hopeful that we will be able to meet those requirements with the expanded solar project on Decatur and to be able to leverage these funds for our most vulnerable community members.”

Bouchey said the existing infrastructure on Decatur was a main reason OPALCO chose the island for another project as well as that, unlike many areas in the county, it has land-use designation that allows for this type of project. [Ed.: Reference to possibility of conditional use permit deleted; not relevant.] 

Lamb, however, believes the company picked the island for other reasons. The island only has 142 active registered voters, according to County Elections Manager Camolyn Armstrong. That’s less than 1% of the county’s 15,066 voters. 

“They just certainly were not going to let little old Decatur stop them. And there aren’t very many people here anyway, they could make it happen,” Lamb said. “But then we pushed back and pushed back hard.”

Around 20 Decatur residents chartered a boat from Decatur to Friday Harbor to give public comment during two San Juan County Council meetings earlier this year. Residents spoke against the project and a proposal to lease an additional three acres of county-owned property to OPALCO. 

During the second of those meetings, county commissioners voted to cancel a vote on lease following a request from OPALCO to do so. 

“I don’t trust them an inch based on what I’ve seen and heard from them,” Dennis Jenkins, who lives across from OPALCO’s existing Decatur solar grid, told the council during a May meeting. “We all moved to Decatur for a specific reason. We want that kind of environment. It’s rural, the forest; it’s a beautiful place to live. And for OPALCO to come in and do what they’re proposing to do, it’s totally wrong.”

‘Somebody else needs to take a turn’

Decatur residents also worry about the project’s size relative to that of the island’s and that the island is taking on an outsized share of the county’s energy production. 

Decatur Island is about 3.5 square miles, or 2,240 acres. OPALCO’s 23-acre parcel makes up about 1% of the island’s acreage.  Proportionally sized property on San Juan Island, for example, would be just over 350 acres. 

“It’s simply not proportional size-wise for our island,” Lamb said, adding that the parcel is in a heavily forested area in the center of the island 

OPALCO says it will not clear the entirety of the parcel, estimating about 8 acres will be cleared of trees. “The remaining area will be wetland protection and wetland setback protection areas,” states the co-op’s website. “We will also have visual landscaping barriers to make the view from the road aesthetically pleasing.”

Residents also say they’ve done their fair share when it comes to solar in the San Juans. The existing solar project on Decatur is OPALCO’s only solar project, although over 800 individual members throughout the islands also generate renewable energy tied to the OPALCO grid. 

“We already took the first turn,” Lamb said. “Somebody else needs to take a turn. Come back and bother us later; come back and bother us after you’ve bothered a few other islands. It’s not fair to overburden our island.”

OPALCO maintains that the project would not over-saddle the island. According to an FAQ about the project, the co-op expects all islands needing about 30% increases in electricity and that the proposed project would not be more than that projected increase. 

“OPALCO remains committed to the cooperative principles which emphasizes fairness as a key tenet, so we are not asking Decatur to shoulder more of this burden,” the FAQ reads.” OPALCO is looking to put multiple microgrids on all the major islands.”

Cunnington believes many residents would support a solution like installing panels under existing power lines — a solution OPALCO will explore in its feasibility study. 

What’s next for the project? Bouchey said OPALCO is preparing environmental and land-use reports and submitting permits to expand the current microgrid. Once the reports are complete, she said the company will hold an in-person meeting with Decatur residents. 

“The final step will be for OPALCO leadership to take all the information into account and make the final decision on whether to move forward on this project,” she said in an email. 

— By Sydnee Chapman 

Also read in Salish Current:

• “High energy costs, delayed tax credit pose hurdles,” Aug. 12, 2024
• “Battery farms, energy industry’s new darling, lining up to enter PNW,” Sept. 5, 2024
• “Pasture or power? Solar talk on San Juan Island,” April 8, 2024
• “Green hydrogen plans take shape for former Alcoa site,” Jan. 24, 2024
• “New thinking, new technology needed for a greener future,” Dec. 11, 2020